Where Ke enters the calculation
Under outlet control, the head needed to push the flow through the barrel is the sum of the entrance loss, the friction loss and the exit loss (HDS-5, Section 3.2):
where V is the barrel velocity, L the barrel length, R the hydraulic radius of the full barrel and n its Manning's roughness. The headwater is then the outlet water level plus H, less the barrel's fall. Ke is the only term that depends on the inlet; a square-edged opening loses half a velocity head, a well-rounded or bevelled one a fifth. Use these values with the culvert calculator, which checks both inlet and outlet control and reports which governs.
Ke by barrel and inlet
The values the culvert calculator offers for each shape and material:
| Barrel and inlet | Ke |
|---|---|
| Circular pipe, concrete | |
| Square Edge with Headwall | 0.5 |
| Groove End with Headwall | 0.2 |
| Groove End Projecting | 0.2 |
| Projecting, square-cut end | 0.5 |
| Beveled Ring | 0.2 |
| Mitered to Slope | 0.7 |
| Circular pipe, corrugated metal | |
| Headwall | 0.5 |
| Projecting | 0.9 |
| Mitered to Slope | 0.7 |
| Beveled Ring | 0.2 |
| Circular pipe, smooth-wall HDPE | |
| Groove End with Headwall | 0.2 |
| Groove End Projecting | 0.2 |
| Square Edge with Headwall | 0.5 |
| Projecting | 0.9 |
| Circular pipe, PVC | |
| Groove End with Headwall | 0.2 |
| Groove End Projecting | 0.2 |
| Square Edge with Headwall | 0.5 |
| Projecting | 0.9 |
| Box culvert, concrete | |
| Headwall, Square Edge | 0.5 |
| Headwall, Chamfered | 0.2 |
| Wingwalls 30-75° | 0.4 |
| Wingwalls 10-25° | 0.5 |
| Projecting | 0.7 |
| Box culvert, corrugated metal | |
| Headwall | 0.5 |
| Projecting | 0.9 |
HDS-5 does not list plastic pipe separately. The calculator treats smooth-wall HDPE and PVC like concrete pipe for headwalls and groove ends, and like thin-walled corrugated metal when the end projects from the fill. The box-culvert value of 0.7 labelled Projecting corresponds to the HDS-5 row for wingwalls parallel to the barrel (extensions of the sides) with a square-edged crown.
HDS-5 Table C.2 in full
| Type of structure and design of entrance | Ke |
|---|---|
| Concrete pipe | |
| Projecting from fill, socket (groove) end | 0.2 |
| Projecting from fill, square-cut end | 0.5 |
| Headwall or headwall and wingwalls: socket end of pipe (groove end) | 0.2 |
| Headwall or headwall and wingwalls: square edge | 0.5 |
| Headwall or headwall and wingwalls: rounded (radius = D/12) | 0.2 |
| Mitred to conform to fill slope | 0.7 |
| End section conforming to fill slope | 0.5 |
| Bevelled edges, 33.7° or 45° bevels | 0.2 |
| Side- or slope-tapered inlet | 0.2 |
| Corrugated metal pipe or pipe arch | |
| Projecting from fill (no headwall) | 0.9 |
| Headwall or headwall and wingwalls, square edge | 0.5 |
| Mitred to conform to fill slope, paved or unpaved slope | 0.7 |
| End section conforming to fill slope | 0.5 |
| Bevelled edges, 33.7° or 45° bevels | 0.2 |
| Side- or slope-tapered inlet | 0.2 |
| Reinforced concrete box | |
| Headwall parallel to embankment (no wingwalls), square-edged on three edges | 0.5 |
| Headwall parallel to embankment, rounded on three edges to radius D/12 or B/12, or bevelled on three sides | 0.2 |
| Wingwalls at 30° to 75° to barrel, square-edged at crown | 0.4 |
| Wingwalls at 30° to 75° to barrel, crown edge rounded to D/12 or bevelled top edge | 0.2 |
| Wingwalls at 10° to 25° to barrel, square-edged at crown | 0.5 |
| Wingwalls parallel (extension of sides), square-edged at crown | 0.7 |
| Side- or slope-tapered inlet | 0.2 |
End sections conforming to the fill slope are the precast or prefabricated flared ends supplied with pipe; HDS-5 notes they performed comparably to headwalls in tests. A mitred end is cut to the embankment slope with no flare and loses more.
Manning's n for culvert barrels
| Barrel material | Minimum | Typical | Maximum |
|---|---|---|---|
| Concrete | 0.010 | 0.012 | 0.015 |
| Corrugated Metal (CMP) | 0.021 | 0.024 | 0.030 |
| HDPE (smooth interior) | 0.009 | 0.010 | 0.012 |
| HDPE (corrugated interior) | 0.018 | 0.022 | 0.025 |
| PVC | 0.009 | 0.010 | 0.011 |
| Steel | 0.010 | 0.012 | 0.014 |
The calculator uses the typical value unless you enter your own. Corrugated metal varies with the corrugation profile and whether the invert is paved; use the manufacturer's value for the pipe you specify. For open channels upstream and downstream of the culvert, see the Manning's n table.
Common questions
What is the entrance loss coefficient for a projecting pipe?
Does Ke matter in inlet control?
What Manning's n should I use for a culvert barrel?
How much does the entrance loss add to the headwater?
Sources
- Schall, J.D., Thompson, P.L., Zerges, S.M., Kilgore, R.T. and Morris, J.L. (2012) Hydraulic Design of Highway Culverts, Hydraulic Design Series No. 5 (HDS-5), 3rd ed. FHWA-HIF-12-026. Federal Highway Administration. Section 3.2 and Appendix C, Tables C.1 and C.2.
- Norman, J.M., Houghtalen, R.J. and Johnston, W.J. (1985) Hydraulic Design of Highway Culverts, HDS-5, 1st ed. FHWA-IP-85-15. Federal Highway Administration.
- American Concrete Pipe Association (2011) Concrete Pipe Design Manual. Irving, Texas.
The values are the ones Delta Hydro Studio's calculators use. Last reviewed . Check them against the design manual your project is reviewed under.