Using the calculator above
Start by choosing what the stone protects, because each application has its own equation and inputs. The calculator opens on the bend example worked below: bank revetment on the outside of a bend, a channel average velocity of 2.5 m/s, a toe depth of 2.0 m, a 2H:1V bank, angular quarried rock with a specific gravity of 2.65 and a safety factor of 1.1, on a bend of 60 m centreline radius with a 20 m water-surface width upstream. Enter the bank slope as horizontal per 1 vertical; the angle it makes with the horizontal is shown under the field.
The culvert outlet apron opens on the second example: 2.5 m³/s from a 1200 mm pipe with 0.3 m of tailwater and subcritical flow in the barrel. A bridge pier needs the velocity, whether it is a channel average or already local at the pier, and for a channel average the pier’s location factor; an abutment needs the velocity and depth at its toe.
Each result gives the required D50, the smallest FHWA class whose lower D50 bound meets it (for an apron, the HEC-14 class and the apron’s length, depth and widths), the layer thickness, and the class’s D15 to D100 band plotted against the required size. The US customary switch converts every input and result.
One equation per failure mode
Riprap sizing has no single formula. FHWA HEC-23 and HEC-14 give a different relationship for each place stone is used, because a different force moves the stone in each place. Studio’s riprap tool covers seven applications; the free calculator above runs channel revetment, bridge piers, bridge abutments and culvert outlets:
| Application | What it protects | Source relationship |
|---|---|---|
| Channel revetment | A channel bank, bed slope under about 2% | HEC-23 DG-4, eqns 4.1 and 4.2 |
| Channel spur | The nose of a spur or groyne | HEC-23 DG-2 §2.2.9: DG-4 sizing at = 1.25 |
| Bridge pier | A pier against local scour | HEC-23 DG-11, eqns 11.1 to 11.3 |
| Bridge abutment | An abutment or guide bank | HEC-23 DG-14, eqns 14.1 and 14.2 |
| Culvert outlet | The apron below a culvert outlet | HEC-14 §10.2, eqns 10.4 and 10.5, Table 10.1 |
| Open-bottom culvert | The entrance to an arch or three-sided culvert | HEC-23 DG-18, eqn 18.1 |
| Wave attack | A slope exposed to waves | HEC-23 DG-17, eqns 17.8 and 17.9 (Hudson) |
Every result goes through the same last step: the computed D50 is matched to a standard FHWA gradation class and given a minimum layer thickness, so the output is a specification a quarry can supply.
The HEC-23 bank revetment equation
Channel revetment is the application most designs start with. HEC-23 Design Guideline 4 sizes the stone from a Froude-type group at the toe of the bank:
| Symbol | Meaning | Units / values |
|---|---|---|
| , | Stone size with 30% and 50% finer by weight | m |
| Local flow depth at the toe of the bank | m | |
| Design velocity, 20% up the bank from the toe | m/s | |
| Safety factor | HEC-23 DG-4 recommends 1.1; it must exceed 1.0 | |
| Stability coefficient | 0.30 angular, 0.375 rounded stone | |
| Velocity distribution coefficient | 1.0 straight or inside bend; outside bend; 1.25 below a concrete channel, at a dike end and at a spur | |
| Thickness coefficient | 1.0 at standard layer thickness | |
| Side-slope factor (EM-1601), ; 1.0 for | – | |
| Bank angle from horizontal | degrees | |
| Rock specific gravity | 2.65 typical quarried stone | |
| Gravitational acceleration | 9.81 m/s² |
On the outside of a bend the channel-average velocity is raised to the velocity 20% up the bank, which HEC-23 DG-4 defines under eqn 4.1 as for a natural channel, where is the centreline bend radius and the water-surface width upstream. Both the bend factor and reach 1.0 at about . (A trapezoidal channel uses , which Studio offers.) Below the calculator evaluates them at 2 and reports that it did, rather than extrapolating.
Two features of the equation drive most design decisions. The 2.5 exponent means a 20% error in velocity becomes about a 50% error in stone size, so the velocity deserves more care than any other input. And falls as the bank steepens: 0.98 on a 3H:1V bank, 0.87 on 2H:1V, 0.72 on 1.5H:1V, the steepest slope the factor is given for. A bank at or steeper than the rock’s angle of repose is unstable before any water reaches it, so the calculator refuses it and tells you to flatten the slope; because the angle of repose depends on , the check is iterated with the size.
The equation is dimensionally homogeneous. The constants apply unchanged in SI and in US customary units, so there is nothing to convert.
The other six applications
Bridge piers
HEC-23 eqn 11.1 gives . With a channel-average velocity, (eqn 11.2); with a local or maximum velocity at the pier, from a 2D model for example, (eqn 11.3). The pier-shape factor is 1.5 for a round nose and 1.7 for a square face and applies in both cases. The location factor runs from 0.9 for a pier near the bank in a straight reach to 1.7 for a pier in the main current around a sharp bend; the stone goes as , so set it for where the pier sits. The layer is at least 3 thick, in a pre-excavated hole with its top flush with the bed (DG-11 §11.5).
Bridge abutments
HEC-23 switches equation at a Froude number of 0.80. Below it, with = 0.89 (spill-through) or 1.02 (vertical wall). Above it, with = 0.61 or 0.69. The two forms meet at 0.80, so the switch does not step the size.
Culvert outlet riprap aprons
HEC-14 eqn 10.4 sizes the apron stone:
where is the flow through one barrel (m³/s), the barrel diameter or rise (m) and the tailwater depth (m). Tailwater sits in the denominator, so a free outfall would demand infinite stone. HEC-14 limits the tailwater to , so the calculator evaluates at when the actual tailwater is lower and at when it is higher. For supercritical flow in the barrel, the stone is sized on (eqn 10.5), where is the normal depth. Eqn 10.4 assumes a rock specific gravity of 2.65; for other rock is scaled by .
The apron is then dimensioned from HEC-14 Table 10.1, by the smallest riprap class whose is at least the required size:
| Class | (mm) | Apron length | Apron depth |
|---|---|---|---|
| 1 | 125 | 4 D | 3.5 |
| 2 | 150 | 4 D | 3.3 |
| 3 | 250 | 5 D | 2.4 |
| 4 | 350 | 6 D | 2.2 |
| 5 | 500 | 7 D | 2.0 |
| 6 | 550 | 8 D | 2.0 |
The width is 3 D at the outlet, flaring to at the end of the apron (HEC-14 Fig 10.4).
Open-bottom culverts, spurs and wave attack
These three run in the Studio tool rather than the free calculator. Open-bottom culverts use HEC-23 eqn 18.1 with the envelope coefficient (0.68) by default, or the best-fit curve (0.38) for checking an existing structure. Spurs reuse the revetment equation with = 1.25, as HEC-23 DG-2 §2.2.9 directs; an optional site multiplier on the approach velocity is there for a nose with evidence of faster flow. Wave attack uses the Hudson equation with = 2.2 for riprap, breaking or not, and (eqn 17.9).
Inputs and where they come from
- Velocity and depth. For a prismatic channel, take normal depth and mean velocity from the Manning’s equation calculator. Where the reach is controlled by a downstream structure, use a backwater profile from the gradually varied flow calculator instead, because normal depth will be wrong.
- Bend geometry. Measure along the channel centreline and as the water-surface width just upstream of the bend, both at the design flow.
- Bank angle. From the design cross-section. 2H:1V is 26.6°; 1.5H:1V is 33.7°.
- Culvert flow, diameter and tailwater. From the culvert design. The culvert calculator gives the outlet velocity and flags when outlet protection is needed. For a supercritical barrel, take the normal depth from the same design.
- Pier location factor. From the pier’s position in the flow: 0.9 near the bank in a straight reach, up to 1.7 in the main current around a sharp bend.
- Specific gravity. 2.65 unless the quarry has tested the rock.
Worked example: revetment on an outside bend
A channel carries its design flow at a mean velocity of 2.5 m/s and a toe depth of 2.0 m. The bank is 2H:1V (26.6°), protected with angular quarried rock ( = 2.65). The reach is an outside bend with = 60 m and = 20 m, so = 3.0. The safety factor is 1.1, as HEC-23 DG-4 recommends, and the thickness coefficient 1.0.
- Design velocity: m/s.
- ; .
- Side slope: .
- = 324 mm, so mm.
- The smallest class with a lower D50 bound of at least 389 mm is Class V (432 mm). Class VI is offered as the conservative alternative. The rock’s angle of repose at that size, about 35°, is steeper than the 26.6° bank, so the bank is stable.
- Layer thickness = max(1.5 × 521, 914, 300) = 914 mm, governed by the Class V maximum D100.
The same channel on a straight reach needs a D50 of 120 mm (Class I, 305 mm layer). The bend raises the toe velocity by half and, with the larger , more than triples the stone.
For a culvert outlet apron: = 2.5 m³/s from a 1.2 m pipe with 0.3 m tailwater and subcritical flow in the barrel. The tailwater is below 0.4D, so the equation is evaluated at 0.48 m. The discharge group is 0.506, giving = 242 mm. That is HEC-14 riprap class 3 (250 mm), so the apron is 6.0 m long (5D) and 600 mm deep (2.4 × 250 mm), 3.6 m wide at the outlet and 7.6 m wide at its end. The equivalent HEC-23 gradation is Class III.
FHWA riprap gradation table (Class I to X)
The calculator matches each result against the ten FHWA standard classes of HEC-23 Volume 2, Design Guideline 4, Table 4.1, which follows NCHRP Report 568. Each class is named by its nominal D50 and limited by a minimum and maximum D15, D50 and D85 and a maximum D100. Values are the published inch sizes converted at 25.4 mm/in, shown as minimum–maximum in millimetres.
| Class | Nominal D50 | D15 (mm) | D50 (mm) | D85 (mm) | D100 max (mm) | D50 (in) |
|---|---|---|---|---|---|---|
| I | 152 mm (6 in) | 94–132 | 145–175 | 198–234 | 305 | 5.7–6.9 |
| II | 229 mm (9 in) | 140–198 | 216–267 | 292–356 | 457 | 8.5–10.5 |
| III | 305 mm (12 in) | 185–267 | 292–356 | 394–470 | 610 | 11.5–14.0 |
| IV | 381 mm (15 in) | 234–330 | 368–445 | 495–584 | 762 | 14.5–17.5 |
| V | 457 mm (18 in) | 279–394 | 432–521 | 597–699 | 914 | 17.0–20.5 |
| VI | 533 mm (21 in) | 330–470 | 508–610 | 699–826 | 1067 | 20.0–24.0 |
| VII | 610 mm (24 in) | 368–533 | 584–699 | 787–940 | 1219 | 23.0–27.5 |
| VIII | 762 mm (30 in) | 470–660 | 724–876 | 991–1168 | 1524 | 28.5–34.5 |
| IX | 914 mm (36 in) | 559–800 | 864–1054 | 1194–1410 | 1829 | 34.0–41.5 |
| X | 1067 mm (42 in) | 648–927 | 1016–1232 | 1384–1638 | 2134 | 40.0–48.5 |
Selection uses the lower D50 bound, the smallest stone the class guarantees. Thickness uses the upper bound, because the layer has to hold the largest stone the class allows. A required D50 above 1016 mm returns no class, with the reason stated, rather than an extrapolated Class XI.
Limitations and when to use something else
- The revetment equation applies to bank revetment in channels with a bed slope below about 2%, the limit the FHWA Hydraulic Toolbox puts on this application. A roadside or drainage channel lined over its whole bed and banks is a lining design, whatever its slope: use the HEC-15 channel lining calculator.
- The calculator sizes stone; it does not compute scour. Where contraction scour plus long-term degradation at a pier is deeper than 3 D50, the layer has to be thickened to that depth (HEC-23 DG-11 §11.5), which needs a separate scour analysis.
- HEC-14 riprap aprons serve culverts of 1 500 mm (60 in) or less, with tailwater from 0.4 D to 1.0 D. Outside those the result is flagged as indicative and a designed energy dissipator is often the better answer.
- Filter design (HEC-23 DG-16), embankment overtopping and wind-generated design waves are not yet available. Their coefficient tables are not in the tool, and the calculator does not substitute estimates for them.
- Wave attack is sized with Hudson only. HEC-23 DG-17 also gives the Pilarczyk method and adopts the larger stone; check it by hand for a governing design.
- Results are only as good as the velocity. Where flow concentrates at a structure or around a bend, a 2D model velocity is worth the effort.
What a free Studio account adds
- All seven applications. Spurs, open-bottom culverts and wave attack join the four above, in the same workspace.
- Checks and derivation. A checklist (bank stability, fitted range, tailwater limits, gradation) and a step-by-step derivation for every result.
- Linked inputs. Velocity and depth can be sent straight in from the Manning’s equation tool (Channel Analysis), and the Culvert Designer sends its outlet velocity across.
- Sample designs. Worked cases to load and adapt, from a bend revetment to a pier.
- Saved and reported. Designs save to a project alongside the hydrology and culvert work they depend on, and export as a Word, Excel or PDF report that carries the derivation and checks for a design review.
Common questions
How do you calculate riprap size?
Which riprap class do I need for my D50?
How long should a riprap apron be at a culvert outlet?
How thick should a riprap layer be?
Does riprap need a filter layer?
Should I use HEC-23 riprap sizing or HEC-15 rock lining?
design_riprap and select_riprap_gradation. The agent passes the inputs, the engine does the calculation, and the record is saved to your project for you to review.
References
- Lagasse, P.F., Clopper, P.E., Pagán-Ortiz, J.E., Zevenbergen, L.W., Arneson, L.A., Schall, J.D. and Girard, L.G. (2009) Bridge Scour and Stream Instability Countermeasures: Experience, Selection, and Design Guidance, Volume 2, Hydraulic Engineering Circular No. 23 (HEC-23), 3rd ed. FHWA-NHI-09-112. Federal Highway Administration, Washington DC.
- Lagasse, P.F., Clopper, P.E., Zevenbergen, L.W. and Ruff, J.F. (2006) Riprap Design Criteria, Recommended Specifications, and Quality Control. NCHRP Report 568. Transportation Research Board, Washington DC.
- Thompson, P.L. and Kilgore, R.T. (2006) Hydraulic Design of Energy Dissipators for Culverts and Channels, Hydraulic Engineering Circular No. 14 (HEC-14), 3rd ed. FHWA-NHI-06-086. Federal Highway Administration, Washington DC.
- Kilgore, R.T. and Cotton, G.K. (2005) Design of Roadside Channels with Flexible Linings, Hydraulic Engineering Circular No. 15 (HEC-15), 3rd ed. FHWA-NHI-05-114. Federal Highway Administration, Washington DC.
- Federal Highway Administration (2021) FHWA Hydraulic Toolbox User's Manual, v. 5.1. FHWA, Washington DC.
- US Army Corps of Engineers (1984) Shore Protection Manual, 4th ed. Coastal Engineering Research Center, Vicksburg, Mississippi.
Last reviewed by the Delta Hydro engineering team.